Thursday, May 5, 2016

Davis Caves construction detailed overview from 1/08/2009



Spring of 2005 we requested pricing information from Davis Caves for building in the area in 1-3 years and on 6/06/05 received a price of ~$84/square foot.

March of 2007 we met with Ruthanne Davis to discuss our needs and why we should hire them over others.  Finished building cost  was given as ~$100/square foot.  In July Marty visits the job site and we pay him $3000 non-refundable deposit that is to be applied to construction costs. August 2007 the finished price goes up to $120/square foot.  

When visiting the site we discussed site prep and tree removal in particular, at that time he gave us a figure, I believe it was $3000, for this work.  We told him we already had a cheaper bid in hand that we would use instead.  At that time Marty Davis offered to include the work in the contract price if we let him take the wood, I replied asking if he would be willing to leave a portion of the wood for our use since our plans included a fireplace.  He agreed.  Each time we received a description of the job I took the statements that tree removal and site prep would be included as evidence of this agreement.

When the work was done he did indeed take most of the wood leaving us a small stack, as if he remembered the agreement and then he demanded $9700 for the work.  In fact he now uses removing the wood from the property as a reason he is asking for so much for the work.  If we were paying him we would have expected the wood (our property) to be left for us.
The wood cutting was done, to the best of my knowledge, by a crew of 3 and finished in two days.  Later he cited labor costs for additional work at $30/hour per worker. 
We had trouble getting financing for an earth sheltered home and the bank appraisals kept coming back thousands of dollars under the construction cost.  The cost was also more than we were comfortable with so we went for conventional construction in the end.  We closed on the construction loan 4/23/08.

Trees cut on 5/20-21/08.  Area cleared, preparing to break ground 6/12/08.  Footers in 6/21/08.
Demand for additional $9700 for clearing/removal of trees and “dirtwork” for drive 6/23/08. I showed Marty his signed description of materials showing the tree removal included in price, he claimed that document had no bearing because prices were not on it, he was angry said he did not remember writing that said he would have to decide whether he would continue the job. We offered to pay him $3000 for this work, even though we felt we were not obligated to do so, when the job was finished provided that there were no cost overages or other “surprises” in the building process.  Marty assured us that all the other prices good and that there were no other surprises.
Basement walls poured (curing) 6/28/08. Forms off, basement plumbing rough in 7/02/08.  Basement plumbing rough in finished, gravel in place. Prepping to pour concrete floor 7/08/08.  Floor poured 7/09/08.

Around this time Marty told me that his supplier would not sell him an electric furnace to install as per the specifications of our house.  We could pay him more for a heat pump (that we actually preferred, and had originally asked for, but they said the earth sheltered house would need so little heat that it did not make sense to upgrade from normal furnace and we wanted all electric) or find our own HVAC contractor he also said that his septic contractor had fallen through and we should hire our own septic contractor.  We did on both counts.  Marty had already pulled out $3000 from the septic line item (supposedly needed for ordering materials for the septic system) and after the work was done a second payment was made to Marty to give him the total amount needed to pay the septic contractor (early September draw).

7/10 or 7/11 I was asked for exact window sizes and placement so wall framing could start soon and when I delivered the lower level figures I commented to Adam Davis that their prices must be much better than those on the Andersen Window web site, as I could not get the windows for the price in the Verified Contractor's Statement (that I refer to as the contract).  Marty let me know that the windows were going to cost significantly more than the line item for windows (and doors) of $7300.  We worked out a compromise where we downgraded the windows from series 400 to series 200, reduced the number of windows and doors, exchanged some windows for a cheaper style and purchased the interior doors ourselves.  This got the cost down to about $7400 using the price list from Marty and the Andersen Windows web site prices for the windows not listed on Marty's list.  Marty then supplied us with $1560 to purchase the exterior doors of our choosing.  Marty drew $3000 from the window line item as down payment for the window order, and supposedly place that order in mid-July.  At the time of the second draw in late July Marty asked to put $4800 on the statement for the tree removal/etc.  I refused and he said that he would trust us to take care of it at the end of the project.

Framing continued, exterior walls were built and there was a long wait for the roof trusses.  By 8/26/08 roof was on (no shingles), by 8/29/08 wiring was being started.  We selected siding and shingles from samples and brands provided by Marty.  By 9/13/08 the shingles were on as was house wrap.  L***** went into the hospital on 8/24/08 with *****, was there until 9/06/08. 
9/11/08  I got a call from S***** from ***** Ready-Mix telling me that they had not received payment from Marty for concrete and that she was having a hard time reaching him on the phone, would I have him contact her?  (this might have been a second call from her, she might have made a similar call earlier, probably August, I do not recall clearly) I called Marty passed this on and inquired as to why this had not been paid as he had drawn the funds for it.  He explained that he had already taken care of it, but S***** must not have gotten it yet.
We hired a local HVAC contractor to install heat pump system, his price was $8000, which is $2000 over the contract price.  He finished the rough in and billed us for the first half. 
L*****'s recovery was difficult after her release from the hospital and we found a specialist in ***** (out of state) to consult.  We were there on 9/24/08 when S***** called me again, saying that they had still not received payment and if they did not they would have to put a lien on our property.   We called Marty and left a message instructing him to call us and explain why Ready-Mix had not been paid.  We got an email saying he had called her and was sending a check that weekend.
On 9/30/08 we received an email from Marty saying that he could not continue working on our house until we “get settled up on the bill for the removal of the trees and the cutting in of the driveway.”  The next day we visited the job site to find all of his tools and equipment gone.  That day we went to ***** Title Co. to inform them of the situation and confirmed that ***** Ready Mix had still not received payment, later we confirmed that the septic system had not been paid for either.
I emailed Marty on 10/02/08 saying I was not certain what payment he was waiting for, but to work with us to resolve the issue.  On 10/10/08 I emailed again asking what he was asking for and got a response on 10/11/08 saying that we needed to pay him what he felt was owed to him.  On 10/13/08 he emails promising to get the figures together of what he wants.  On 10/14/08 he demands “full” payment of tree removal etc. and other money from septic line item and his remaining profit on the project.  On 10/15/08 he finally says he wants the full amount as per his “original bill” he thinks it is $9800.
I had a meeting with (loan officer) who recommended paying him off to get back to work and she tried to get a meeting for Marty and I with her and the title co.  Marty is never available so we finally get a conference call on 10/29/08.  During this call Marty admits to not paying bills to force me to pay him more money, he felt this was the only way he had enough leverage to get the extra money from us.  I am unwilling to pay him more money at this time, but I had done the math and knew that he had at least $12000 in unpaid bills and a lien that would result in foreclosure on 12/01/08.  Marty was unwilling to return to work or pay the bills for fear he could no longer force me to pay him extra money.  (loan officer) suggested that I pay the money into an escrow account that would be guaranteed t be paid to Marty when he finished the job and if he had cleared the unpaid bills before 12/01/08.  We both agreed and were left to negotiate the final amount.
In the end I agreed to pay the $9700 with terms such as his paying the unpaid bills before we were foreclosed on.  Marty then refused any agreement short of paying him directly with no conditions.  This was untenable so I paid about $12500 in unpaid materials and subs, told him to take the $9700 from that, return the rest and get back to work.  First he said he would consult his schedule, then he asked for another payout.  I suggested that he put together the payout he thought he was due and that we would meet with the bank and title company to discuss it.  We have heard nothing from him since.
I tracked down Marty's supplier, called them on 12/30/08 and learned that our windows were there, but nothing had been paid on them (Marty had drawn $3000 for them) and they would be putting a mechanic's lien on our property in 30 days.  The bill for the windows was ~$9000 and they would check their records to see what else was on Marty's account for our project that they would be demanding from us.  I told them I would work to get them $4000 in a few weeks if that would ease the pressure on them placing the lien, he said it would.  I spoke to J***** of J***** Lumber 217-***-****.  He told me that he did not think there was much else on the account, but he has yet to contact me with the amount.  My understanding is that he has been a supplier for Marty for many years and Marty currently has other projects ongoing on account with him.
Current status of house is very near what is was on 9/13/08.  There has been a small amount of plumbing work done, but the electrical is unfinished and still in house wrap with no windows and no ability to do much more inside until they are installed.
On 1/06/09 I got copies of the lien waivers collected by ***** Title Co. And, other than those we have supplied, they are all signed off by Davis Caves, nothing from suppliers or subcontractors.  Additionally the first draw of $24000 only has a single waiver for $8000.  The second draw has waivers for all but the plumbing, which was paid to Marty despite the line item listing the sub as payee.  (Sub) has also worked with Marty for many years so I have avoided calling him to ask if he received the money as I fear it will give him the excuse to ask for more regardless.  (bank) maintains that the next payout cannot be made until all lien waivers from the previous draw have been collected. 
When we questioned (title officer) (10/31/08, before we had the copies of the collected waivers) she said (title company) had done everything correctly and the problem was not their fault.  Marty said he was doing everything and they collected lien waivers from him. 
When we signed the paperwork at ***** Title we were told that they made sure that the payouts were done correctly.  Marty had to show receipts for materials and lien waivers for everything.  We were also told that if the actual cost was less than the line item the difference stayed in the loan and that Marty was not entitled to any remainders.  That we could apply funds from any underages to overages elsewhere.

Also (bank) states our contract with them makes us liable for all of their legal costs if they go to court.  They also informed me that Marty can sue them if they pay anyone else the funds to build with, and that he has up to two years to do so.  

My research seems to indicate that the bentonite waterproofing was not used as Marty specified..
Summery of collected lien waivers (supplied by  ***** Title Co., supposed to be all collected waivers, received 1/06/09).
Dated              From                           Amount          For
7/29/08            Davis Caves Inc.         $8000.00         capenter** labor and other labor and materials
8/23/08            Davis caves Inc           $15500.00       lumber and other labor and material
8/23/08            Davis caves Inc           $1400.00         floors and drives and other labor and material
8/23/08            Davis caves Inc           $2500.00         footings and walls and other labor and material
8/23/08            Davis caves Inc           $3000.00         sewer/septic and other labor and material
8/23/08            Davis caves Inc           $1000.00         excavating/grading and other labor and material
8/23/08            Davis caves Inc           $7560.00         capenter** labor and other labor and material
8/23/08            Davis caves Inc           $850.00           electrical and other labor and material
8/23/08            Davis caves Inc           $3560.00         profit/overhead and other labor and material
Subtotal of lien waivers supplied
by Davis Caves Inc.                           $43370.00
9/04/08          Homeowner                $3750.00   flooring and other labor and material
9/04/08          Homeowner                 $390.06    ceramic/plastic wall tile and other labor and material
9/04/08          Homeowner                 $258.49           appliance allowance and other labor and material
11/18/08          S***** Backhoe*         $5089.14         septic system and other labor and material
11/18/08          M***** Ready Mix*   $7169.97         concrete and other labor and materials
11/18/08          Mr. M***** *         $300.00           septic service and other labor and material
*These payments made from (homeowners) and not drawn from the construction loan.
**Spelling on the lien waiver.

No comments:

Post a Comment